Montana Contractor's Gross Receipts Tax on Public Jobs
Last verified: November 24, 2026
If you bid on or perform construction work for a public entity in Montana, the Montana gross receipts tax applies to that work. For public contracts, it is a 1% tax, and the public entity that awards the contract sets much of the paperwork in motion. That makes the contractor's gross receipts tax different from the business taxes most contractors already track.
This guide explains who owes the tax, how the 1% is withheld from your payments, which forms track each contract, and what happens when a filing is late. It is written for prime contractors and subcontractors who need a working picture before money starts moving on a job. Where this guide does not cover a detail, it says so and points you to the agency that can confirm it.
Who Owes the Montana Contractor's Gross Receipts Tax
The Montana Department of Revenue says all contractors and subcontractors must pay a 1% tax on all public construction contracts over $80,000. The $80,000 threshold comes from MCA 15-50-101(3), which defines a public contractor by a contract cost, value or price that exceeds $80,000. That section was amended by Ch. 751, L. 2023.
The core obligation sits in MCA 15-50-205(1). A public contractor must pay the department a license fee equal to 1% of the gross receipts from public contracts during the income year in which it receives payment. The statute calls this a license fee, while the Department of Revenue refers to it as the contractor's gross receipts tax. Late-filing rules and penalty language use the term license fee, so keep both names in mind when you read the statute and the department's forms.
The statute carves out one case: work on a federal research facility is not covered by the license fee under MCA 15-50-205(1). This guide does not cover how other exemptions apply, or how contracts at or below $80,000 are treated in detail. Confirm those points with the Montana Department of Revenue before you bid.
SB 253, signed May 22, 2023, revised the Contractor Gross Receipts 1% tax. Its changes apply to public contracts exceeding $80,000 in value. Check your contract value against that line before you assume the tax applies, and keep in mind that this guide does not cover how change orders or amendments are counted toward the threshold.
How the 1% Is Withheld From Your Payments
In most public jobs, you do not send the 1% yourself on each payment. MCA 15-50-206(2) says the state, county or city for whom you perform public work must withhold 1% of all payments due you and transmit that amount to the department. The withholding happens at the source, so your payment is reduced before it reaches your account.
The awarding public entity usually registers the contract. The department's timeline for that step is within 10 days after the contract is awarded. The same entity usually files withholding returns and remits payment. The department's timeline for that step is within 30 days after the date of a payment to you.
If the public entity does not withhold, the statute puts the duty on you. You pay within 30 days after receiving each increment of payment. Track every payment you receive so you can meet that window.
Key point: If the public entity does not withhold from a payment, the 1% becomes your responsibility, and the 30-day clock under MCA 15-50-206(2) runs from the day you receive that increment.
Forms and Filing Steps for Public Contracts
The Department of Revenue handles these filings through the TransAction Portal (TAP). Three forms cover registration, withholding returns and refunds. The table below shows what each form does, and the steps that follow walk through a typical public contract from award to refund.
| Form | Purpose | How It Is Filed |
|---|---|---|
| Form CGR-1 | Registers the public contract | TransAction Portal (TAP) |
| Form CGR-2 | Files and pays withholding returns, or allocates withholding to subcontractors | TransAction Portal (TAP) |
| Form CGR-3 | Requests a refund of eligible taxes or fees | TransAction Portal (TAP) |
Step 1: Confirm the Contract Falls Under the Tax
Check the contract cost, value or price against the $80,000 line in MCA 15-50-101(3). Contracts that exceed that amount are public contracts subject to the 1% license fee. If your contract sits near the line, confirm the treatment with the Montana Department of Revenue before you commit to a bid price.
Step 2: Verify the Contract Registration on Form CGR-1
The awarding public entity usually registers the contract on Form CGR-1 within 10 days after the contract is awarded. Ask the entity to confirm in writing that the registration was filed. Keep that confirmation with the contract file.
If the entity cannot confirm the registration, contact the Montana Department of Revenue to find out how registration should proceed. This guide does not cover the internal steps the entity takes to file the form.
Step 3: Plan Your Cash Flow Around the 1% Withholding
Plan your cash flow around the withholding, not the gross contract price. The public entity withholds 1% of each payment due you and sends that amount to the department. Your invoices and payment records should show the withheld amount so your books match the department's records.
Step 4: File Withholding Returns and Pay Within 30 Days on Form CGR-2
Form CGR-2 files withholding returns and pays the withholding, or allocates withholding to subcontractors. The awarding entity usually files and remits within 30 days after a payment to you. If the entity did not withhold, you pay within 30 days after receiving each payment increment.
A late filed CGR-2 carries a penalty. The penalty is covered in its own section below, so build the 30-day window into your bookkeeping from the first payment forward.
Step 5: Request a Refund or Credit
If you are owed money back, submit Form CGR-3 through TAP. Contractors can use the same form to request a refund of business personal property taxes and certain registration fees for vehicles used in contracting. You can also claim a credit on the Montana Individual Income or Corporate Income Tax return, depending on your filing type.
Subcontractors and Federal Contracts
If you are a prime contractor who brings in subcontractors, you have separate filing duties. A prime contractor registers the subcontract within 10 days and files withholding returns and requests allocations within 30 days after a payment to a subcontractor. Keep the subcontract records and payment dates organized so each allocation matches what your subcontractors receive.
Subcontractors should also track the withholding taken from their own payments. Ask your prime contractor for the allocation details and keep a copy with your records for each public job.
Federal government contracts follow a different path. If a federal government contract is awarded, the federal government will not register, withhold or remit the tax. The prime contractor is responsible for registering and remitting withholding when required. This guide does not cover federal reporting requirements, so confirm them before work begins.
Late Filing Penalties
A late filed CGR-2 is subject to a penalty of 10% of the 1% license fee. Under the department's description, that penalty applies only to CGR-2 allocations under 15-50-206, MCA. Treat late allocations as a real cost to the job, not a minor clerical issue.
This guide does not cover interest charges or other penalties that may apply to late payments or late registrations. Confirm those amounts and any other consequences with the Montana Department of Revenue, since the figures are not part of this guide.
Refunds, Credits and Pass-Through Entities
The 1% gross receipts taxes you previously paid are available for credit and refund for the year they are paid, plus 5 succeeding tax years. Track each year's payments separately so you do not lose track of what is still available. Keep copies of the CGR-2 filings that support each amount.
Pass-through entities need extra care. The Department of Revenue says income tax credits and the Contractor's Gross Receipts Credit cannot be used to offset the pass-through entity tax (PTET) and must be passed to owners. Review the Montana Department of Revenue pass-through entity tax guidance before you allocate credits to owners.
Where the Revenue Goes and the Governing Law
Contractor's gross receipts tax revenue goes to the state general fund. The related laws are 15-50-101 through 15-50-311, MCA, and ARM 42.31.2101 through 42.31.2143. Read those sections when you need the exact wording of a rule, rather than relying on a summary.
For current form versions and filing instructions, check the Montana Department of Revenue contractor's gross receipts tax page. Those instructions control if they differ from anything you read here.
What This Guide Does Not Cover
This guide does not cover how gross receipts are calculated on mixed contracts, how the income year rules apply to unusual payment schedules, or how the contractor's gross receipts tax interacts with other taxes you pay as a business. It also does not cover the local permits, bonding or licensing steps that some public jobs require.
When you hit one of these gaps, contact the Montana Department of Revenue directly. Describe the contract, the payment schedule and the entity that awarded the work so the answer fits your situation.
Frequently Asked Questions
Does the Montana contractor's gross receipts tax apply to every construction job?
This guide covers public construction contracts only. The Department of Revenue says the 1% tax applies to all public construction contracts over $80,000, so check the contract value and the awarding entity before you assume the tax applies.
Who withholds the 1% from my payment?
The state, county or city for whom you perform public work withholds 1% of payments due you and transmits it to the department under MCA 15-50-206(2). If that does not happen, you pay within 30 days after receiving each increment of payment.
What happens if my CGR-2 is late?
A late filed CGR-2 carries a penalty of 10% of the 1% license fee. This guide does not cover interest or other charges, so confirm those with the Montana Department of Revenue.
How do I recover tax I already paid?
Submit Form CGR-3 through the TransAction Portal (TAP), or claim a credit on your Montana Individual Income or Corporate Income Tax return. The 1% gross receipts taxes previously remitted are available for credit and refund for the year they are paid, plus 5 succeeding tax years.
Does a federal contract change who files?
Yes. The federal government will not register, withhold or remit the tax on a federal government contract. The prime contractor is responsible for registering and remitting withholding when required.
Disclaimer
This guide is informational content only and is not legal or tax advice. Rules, forms and deadlines can change, so confirm current requirements with the Montana Department of Revenue and consult an attorney or CPA before you make filing or tax decisions for a specific contract.
Sources
- Montana Department of Revenue: Contractor's Gross Receipts Tax
- Montana Department of Revenue: Pass-Through Entity Tax
- Montana Code Annotated 15-50-101, 15-50-205 and 15-50-206 (contractor's gross receipts tax statutes)
- Administrative Rules of Montana 42.31.2101 through 42.31.2143